The GPBC Fellowship Hall expansion will increase the usable space along with the addition of two bathrooms with showers and an enlarged kitchen.

  • Day 54: May 30, 2020 Trusses go up!
  • Day 53: May 29, 2020 Framing
  • Day 51 & 52: May 27 & 28, 2020 Shingles, Lumber & Framing begins
  • Day 50: May 26, 2020 Subflooring concrete pouring
  • Days 45 & 46: May 21 & 22, 2020 Flooring preparation. Fellowship Hall Ceiling Lights and Insulation Removal
  • Day 43: May 19, 2020 Fellowship Hall Ceiling Tile Removal & Old Cinder Block Wall Removal
  • Day 39: May 14, 2020 Plumbing & Eaves Removal
  • Day 36 & 37: May 12-13, 2020 Floor Leveling
  • Day 33: May 11, 2020 Lining Foundation
  • Day 32: May 8, 2020 Corner Blocks
  • Day 19: May 5, 2020 Foundation
  • Day 13: April 29, 2020 Cinder Block Preparation
  • Day 12: April 28, 2020 Footing Preparation
  • Day 9: April 25, 2020 Grading & Old Storage Areas
  • Day 8: April 23, 2020 Brick Siding & Sidewalk Removal
  • Day 6: April 21, 2020 Roof Line Preparation
  • Day 5: April 21, 2020 Rained All Day – no work
  • Day 3 & 4: Weekend no work
  • Day 2: April 17, 2020 Temporary Wall in Fellowship Hall
  • Day 1: April 16, 2020 Ground Breaking
  • Day 0: Prior to Construction